Meadowbrook Road Rehabilitation: 10 Mile to 11 Mile
Please note - due to the nature of road construction, inclement weather or other unforeseen circumstances, dates/times may vary. Thanks for your patience as we work to improve our roads.
Updated: October 14, 2025
Start: Summer 2025 (after completion of the 9 Mile Road Rehabilitation project)
Current Status: In Progress
End: Fall 2025
Road Jurisdiction: City of Novi
Progress:
10/14/25: Northbound lane milling is complete. Paving with new asphalt began on Monday, October 13, and is scheduled to continue through Tuesday. The contractor anticipates shifting traffic onto the newly paved northbound lanes either Wednesday or Thursday of this week.
Following this traffic shift, milling of the southbound lane(s) is scheduled to begin on Friday, October 17.
Traffic Impact Note: Please anticipate brief but intensive delays near the 10 Mile intersection for approximately two hours during the milling and paving process. The contractor will utilize flagging control to safely manage traffic during this specific period.
9/29/25: Widening of the road started today. This phase of the project should have a very minimum impact to traffic. We anticipate this taking 2-3 weeks.
Description: The City will be rehabilitating Meadowbrook Road from 10 Mile to 11 Mile Roads (Phase 2). The plan is to rehabilitate the existing pavement by cold milling and repaving with new asphalt; ADA sidewalk upgrades; and updating of existing signage and pavement markings.
Traffic Control/Detour: Southbound traffic will be maintained throughout the duration of the project no matter which side of the roadway is being worked on. Northbound traffic will be detoured east on 10 Mile Road, then north on Haggerty Road, west on 12 Mile Road, and back to Meadowbrook Road.