Start: April 15, 2025
Current Status: Pending
Projected End: November 2026
Project Jurisdiction: Road Commission for Oakland County
Progress:
Starting Phase 1 or Phase 2 construction will depend solely on the success of the utility companies relocating their facilities and Wayne County completing the bridge deck work on the 8Mile/CSX bridge (below), just east of Novi Road which will be closed and traffic west of it will need to utilize Novi Road as a detour.
Description
The Road Commission for Oakland County (RCOC), in partnership with the cities of Novi and Northville, will rehabilitate and reconstruct Novi Road, from 8 Mile to 9 Mile Roads.
Phase 1 - relocate utilities (DTE, Consumers, AT&T, etc.)
Phase 2 - reconstruct the 'curve' between 8 Mile Road and Allen Drive in the summer/fall of 2025
Phase 3 - rehabilitate the remainder of Novi Road from Allen Drive to 9 Mile Road.
There are also plans to add a continuous center left-turn lane throughout this entire section of Novi Road, as well as installation of a High-Intensity Activated Crosswalk or HAWK pedestrian signal just north of Galway Drive.
Road Closures/Detours
Phase 1 - there will be intermittent lane closures specific to the various utility companies.
Phase 2 - will be a hard, full closure of Novi Road at 8 Mile and again at Allen Drive.
Phase 3 - the contractor will maintain one-way, southbound traffic only. Northbound traffic will be detoured to Haggerty, 10 Mile and back to Novi Road.
Since this is an Oakland County project, call RCOC’s Department of Customer Services at (877) 858-4804 or send an email to dcsmail@rcoc.org or visit the RCOC Website www.rcocweb.org for more information.