Wixom Rd Sanitary Sewer: Birchwoods Dr. to Braeburn Ln.
Updated 9/6/24
Start: July 2023
Current Status: In-progress
Projected End: September 30, 2024
Road Jurisdiction: City of Novi
PROJECT STATUS:
The sanitary sewer replacement is complete.
Work at the Wixom Road Lift Station (just south of 11 Mile) is now complete with new pumps, control panel, generator, added storm sewer, and repaving the access driveway. At the Drakes Bay Lift Station, the contractor is getting ready to set the new generator, and swap-out the pumps and control panel.
DESCRIPTION
The Wixom Road Sanitary Sewer Replacement & Pump Station Improvements Project is a necessary public health, safety, and welfare project. The sanitary sewer system in this area is at capacity and needs rehabilitation, and improvement to continue to meet the demands of the surrounding community for sanitary sewage disposal.
The contractor, Pamar Enterprises, had to set up dewatering operations to lower the groundwater level within the construction area to make it safe to lay the new sanitary sewer. Dewatering is no longer necessary.